Commercial Fit-Out Electrical Work in QLD: What Business Owners Need to Know
You’ve signed the lease. The shopfitter or builder has quoted you a number. Somewhere in that quote is a line item for the electrical work — probably vague, probably higher than you expected, and possibly missing things that will come back as variations halfway through the build.
This guide is written for the business owner, not the contractor. It covers what a commercial fit-out needs electrically, who legally pays for what, where the timeline risk actually sits, and what compliance documents you must receive at handover. It applies whether you’re fitting out a shop, a cafe, a consulting suite, a gym or a warehouse — the regulatory stack is the same, and only the load profile changes.
Fit-out type changes the load, not the rules
The legislation and standards below apply identically across commercial premises. What differs is what you’re asking the supply to do — and that’s where quotes diverge.
| Fit-out type | What drives the electrical scope |
|---|---|
| Retail | Feature and display lighting, POS and EFTPOS power, illuminated signage, security circuits |
| Hospitality — cafe, restaurant, bar | Commercial kitchen loads, refrigeration, exhaust, three-phase equipment. The heaviest load profile of any small tenancy |
| Office and professional suites | Density of data and power at each workstation, meeting room AV, lighting control, after-hours HVAC |
| Medical, dental and allied health | Equipment-specific supply, dedicated circuits per treatment room, and in some areas additional requirements for patient treatment spaces |
| Gyms and fitness studios | Cardio equipment circuits, sound and AV, high-bay or feature lighting, 24-hour access control |
| Salons and beauty | Multiple hot appliances at each station, hot water, mirrors and task lighting, ventilation |
| Childcare and education | Outlet placement and protection requirements, compliance-driven lighting levels, higher scrutiny at inspection |
| Warehouse, workshop and light industrial | Three-phase machinery, high-bay lighting, compressed air and plant circuits, often three-phase supply rather than single |
The heaviest-load types — hospitality and light industrial in particular — are where the existing tenancy board most often turns out to be inadequate. A cafe going into a tenancy that previously housed a phone accessories shop is the classic version of this problem.
What a commercial electrical fit-out actually covers
“Electrical” in a fit-out is not one line item. It’s a bundle of separate scopes, each with its own standards, its own certification, and its own way of surprising the budget.
- Switchboard work — upgrading, replacing, or adding sub-circuits to the tenancy board
- General power distribution — outlets serving the floor, back-of-house, staff areas and storage
- Lighting — general illumination plus feature, task or high-bay lighting depending on use
- Illuminated signage — external and internal, often on separate circuits with timers
- Emergency and exit lighting — mandated, and tested six-monthly once you’re trading
- Data and communications cabling — POS or workstations, Wi-Fi access points, security, AV
- Dedicated equipment circuits — clean power for tills and computers, or plant and machinery supply
- Security systems — CCTV cabling, alarm connections, access control
- Staff and amenities supply — kitchenette, hot water, air conditioning circuits
- Air conditioning connection — the HVAC contractor supplies the unit; the electrician connects it
- Testing, certification and documentation — the compliance paperwork that must be handed over at completion
The two-phase build sequence
Every commercial fit-out is built in two electrical phases. Understanding the sequence is the difference between a build that runs on schedule and one that becomes a queue of stopped work.
| Phase | When | What happens | What you should see |
|---|---|---|---|
| Rough-in | After framing, before plaster and cabinetry | Cables run through walls and ceilings, switchboard positioned, conduit installed, junction boxes fixed | Exposed cables, mounting brackets, holes cut for outlets and switches |
| Second fix | After cabinetry, joinery, flooring and painting | Outlets, switches, lighting, signage, equipment supply and emergency lighting installed and terminated. Full testing. Certificates issued | Finished fittings, working lighting, testable outlets, compliance documentation |
The trap: if rough-in is late, the plasterer can’t close up. If second fix is late, nobody can hand over. Electrical is among the most common causes of a fit-out timeline blowing out, because it depends on builder-controlled variables (framing, plaster, joinery) and site-controlled ones (landlord sign-off, meter installation, network approval) at the same time.
The Queensland regulatory stack
Commercial electrical work here sits inside a stack of legislation, regulation and standards. Your contractor must comply with all of it, and you should see it referenced in the quote and the certification you receive.
| Layer | What it is | Relevance to your fit-out |
|---|---|---|
| Electrical Safety Act 2002 | Primary state legislation | Requires all fixed electrical work to be performed by a licensed contractor. Sets the enforcement framework |
| Electrical Safety Regulation 2013 | Regulation under the Act | The operational detail — licensing, wiring rules compliance, testing obligations, certification duties |
| AS/NZS 3000 | The Wiring Rules | Every circuit, protective device, cable and earthing arrangement must comply with the current edition and its amendments |
| AS 2293 | Emergency and exit lighting | Where it must be installed, and the testing regime once you’re trading |
| AS/NZS 3760 | In-service inspection and testing | Method and frequency for test and tag once the premises is operating — note Queensland’s rule differs from other states |
| AS/NZS 3017 | Verification guidelines | How the installation must be tested at completion — insulation resistance, RCD testing, earth continuity |
| EESS | Electrical Equipment Safety System | In-scope equipment supplied for the fit-out — LED drivers, feature lights, signage transformers — must be compliant |
| National Construction Code | Building code | Illuminance on escape routes, emergency lighting placement, building services requirements |
Landlord vs tenant — who pays for what
This is where fit-outs actually blow their budgets. The short answer is read your lease first. The longer answer is that most Australian commercial leases split electrical responsibility along a predictable boundary.
| Electrical scope | Typically landlord | Typically tenant | Notes |
|---|---|---|---|
| Main switchboard for the building | Yes | — | Base building responsibility |
| Mains supply to the tenancy boundary | Yes | — | Includes meter installation in most cases |
| Tenancy switchboard, if separate | Sometimes | Sometimes | Depends on the lease and whether a compliant board already exists |
| Emergency and exit lighting in common areas | Yes | — | Landlord’s ongoing six-monthly obligation |
| Emergency and exit lighting inside your tenancy | — | Yes | Your obligation once you’re trading |
| All power, lighting and data within the tenancy | — | Yes | Everything from the boundary inward is fit-out scope |
| Signage electrical supply | — | Yes | Usually tenant, unless the landlord provides pylon or facade signage |
| HVAC electrical connection | Base unit sometimes | Tenancy connections | Base HVAC often landlord; connections within the tenancy are yours |
| Ongoing test and tag inside the tenancy | — | Yes | Your obligation as the operator of the premises |
Two things to check before signing. First, does the tenancy have sufficient switchboard capacity for your intended use? A hair salon draws more than a bookshop; a cafe draws more than either. Landlords are typically not obliged to upgrade base building infrastructure to suit a specific tenant’s load, so if the existing supply won’t run your business, the upgrade sits in your fit-out budget. Second, will the make-good clause at end of lease require you to remove or restore electrical work? That belongs in your budget on day one, not year five.
Eight scope items to lock down at quoting stage
These are where scope creep, missed quotes and mid-build variations happen most often.
- Switchboard capacity assessment. Existing board rating against the total peak load of your intended fit-out. If the answer is “not enough”, the upgrade is yours — see what drives a switchboard upgrade.
- Number and location of outlets. Equipment positions, back-of-house, storage, staff kitchenette, cleaner’s outlet, signage. Underquoting here is the single most common variation.
- Lighting design. General lux level, feature or task lighting, colour temperature, dimmability and control. Lighting decisions are far more expensive to change after installation than during design, and fitting choice interacts with ceiling type.
- Emergency and exit lighting count and placement. Determined by the standard and the building’s fire engineering report, not by aesthetic preference.
- Data and comms cabling. Number of data points, access point locations, CCTV runs, and how these interact with the ceiling grid.
- Signage circuits. Illuminated signs, timers, and dedicated metering if the landlord separates signage from tenancy supply.
- Air conditioning connection. Supplied by another trade, but the electrical supply, isolation and switchboard integration is your electrician’s scope.
- Testing and certification at completion. The certificate, insulation and RCD results, and emergency lighting commissioning documentation.
If your electrical quote doesn’t address all eight, ask why. Silence on an item doesn’t mean the work isn’t needed — it means it hasn’t been priced, and will surface as a variation.
The most common mistakes
- Undersized switchboard. The board was fine for the previous business but can’t handle yours. Discovered late in the build, it adds weeks as well as cost
- Insufficient outlets at the working position. A register or reception desk needs four to six outlets minimum. Two or three is a lifetime of extension leads
- No lighting design. Fittings picked from a catalogue rather than designed for the space, producing hot spots, dark corners and over-lit storage
- Signage circuit forgotten. Illuminated signage is a separate circuit, often timed, sometimes on landlord-metered supply. Missed at quote, added as a variation
- Emergency lighting under-specified. Legally mandated, non-optional, and often the first item flagged at final inspection
- Data cabling routes conflicting with electrical. Installed by a separate specialist without coordination, producing interference and rework
- No compliance handover. A verbal “it all works” and no certificate. The first fire inspection or insurance audit rejects the installation
- No spare capacity. Engineered for exactly today’s needs, so the first new appliance in year two triggers another switchboard visit
Where fit-outs actually lose time
The six most common timeline killers
- Landlord sign-off delays on tenancy variations before work can start
- A switchboard upgrade discovered mid-build — weeks to arrange, install and connect
- Meter installation delays, since network operator scheduling can add days or weeks
- Coordination gaps between electrician, plasterer, joiner and builder over sequence
- Certification delays at handover, where testing wasn’t scheduled early enough to catch defects before the intended opening day
- Landlord’s fit-out approval sign-off, often required before you can commence trading
The single biggest lever: get the electrical contractor on site before you sign the builder’s contract, not after. A one-hour walk-through with a licensed electrician before you commit to a schedule identifies most of the above.
Shopping centre and managed building approvals
If your tenancy is inside a shopping centre or a managed commercial building, you’re dealing with the building’s own fit-out guide as well as Queensland electrical regulation. That typically requires:
- Pre-approval of the fit-out design by centre or building management before work commences
- Using contractors on an approved list, or contractors who have submitted insurance and licensing documents for approval
- Working within specific hours — often overnight or early morning for noisy or disruptive works
- Landlord sign-off at rough-in and second fix, not only at completion
- Specific requirements for shopfront signage, exit lighting integration with the building’s system, and after-hours access
Centre-based fit-outs typically add several weeks to the timeline for approvals and coordination alone, and the fit-out guide is binding as a condition of the lease. Standalone tenancies skip most of this, but your electrician still needs to confirm base building capacity and the metering arrangement before quoting.
What you should receive at handover
This is not optional and not a “we’ll email it later” item. The licensed contractor is required to test, verify and certify the installation before you take occupancy.
- A certificate of testing and compliance — the certificate that covers electrical installation work in Queensland, issued by the licensed contractor. Note that a certificate of testing and safety is the document for work on electrical equipment, which is a different thing — the two certificates are set out here
- Circuit schedule and switchboard labelling — every circuit identified, permanent labels inside the board
- Emergency lighting commissioning report — initial test results and installation certification
- RCD test results — every safety switch verified as tripping within its required threshold, not merely present. Which device arrangement you’ve been given is worth knowing too
- Insulation resistance test results — per-circuit readings recorded for the compliance file
- Signage and specialty equipment installation records, where applicable
- Statement of workmanship warranty — defining the ongoing service and defect commitment
Keep every one. You’ll want them at the first fire safety inspection, the first insurance renewal, the first fault call-out, and at the end of your lease.
Ongoing compliance once you’re operating
The fit-out doesn’t end at handover. As soon as you open, you’re the person conducting the business or undertaking under Queensland’s WHS framework, and you inherit continuing obligations.
- Six-monthly emergency and exit lighting testing — a full 90-minute discharge test with results recorded. Queensland also attaches deadlines once a fault is found, which catches a lot of operators out
- Test and tag of portable appliances — frequency depends on the environment, and Queensland’s licensing rule differs from other states
- RCD testing — push-button testing by the occupier, plus full electrical testing at the appropriate interval by a licensed electrician
- Switchboard inspection — periodic thermal imaging and physical inspection, particularly for older boards or high-load applications
- Record-keeping — a compliance folder retained on premises and available for inspection
For most operators the efficient way to handle this is a fixed-price preventative maintenance programme that schedules all recurring compliance in advance, so it’s budgeted and doesn’t get forgotten. If the building is strata, our strata and body corporate service covers the common property side.
On the Gold Coast, specifically
Tenancy type tracks location here. Centre-based retail and hospitality through Broadbeach and Robina brings the full approval process. Main-street and strip tenancies through Burleigh Heads, Palm Beach and Coolangatta skip most of it but more often sit in older buildings where the base supply is the constraint. Office and medical suites through Southport and Varsity Lakes tend to be data-density problems rather than load problems, and light industrial through Nerang and Molendinar is usually a three-phase question from the outset.
One local factor worth pricing in wherever you are: coastal tenancies have switchboards and outdoor equipment that corrode faster than the same gear inland, so an existing board’s age tells you less here than its condition does.
Frequently asked questions
What does a commercial electrical fit-out cost on the Gold Coast?
It varies enormously by tenancy size, existing infrastructure, business type and scope, so we don’t publish a range. The single biggest cost driver is whether the existing switchboard needs upgrading, and that can’t be assessed without looking at the board and the intended load. Fixed-price quoting on site is the only reliable way to get a real number for a specific tenancy.
Does this apply to offices and warehouses, or just retail?
All commercial premises. The legislation, the Wiring Rules, the emergency lighting regime and the certification requirements are the same whether it’s a shop, a cafe, a consulting suite, a gym, a salon or a warehouse. What changes is the load profile and the equipment-specific circuits, which is why the quote differs even for tenancies of identical size.
How long does the electrical work take?
Typically two to four weeks of active on-site work for a straightforward fit-out, spread across the build programme with rough-in early and second fix late. Total elapsed time is longer because it’s scheduled around other trades, and centre-based fit-outs run longer again because of the approval process.
Can I use a general handyman instead of a licensed electrical contractor?
No. Under Queensland’s Electrical Safety Act 2002 and the Electrical Safety Regulation 2013, all fixed electrical work must be performed by a licensed contractor. Beyond being unlawful, unlicensed work can’t be certified, which means you won’t have the documentation an inspection or insurance audit will ask for.
Who pays for the switchboard upgrade — me or the landlord?
Usually the tenant. Landlords are typically not obliged to upgrade base building infrastructure to accommodate a specific tenant’s fit-out load. The exception is where the base building doesn’t meet current wiring rules regardless of your fit-out, in which case the cost may be shared. Check your lease, and get a load assessment before signing if the question is significant.
What compliance documents am I entitled to at handover?
At minimum a certificate of testing and compliance from the licensed contractor, a circuit schedule, the emergency lighting commissioning report, and RCD and insulation test results. Keep them in a compliance folder on premises — inspections and insurance audits ask for them, sometimes years after the fit-out.
Can I use residential-grade lighting in a commercial space?
Generally no. Commercial spaces need lighting that meets the illuminance levels for the intended activity, uses fittings rated for extended operating hours, and integrates with emergency and exit lighting. Residential-grade fittings typically don’t meet those requirements.
Planning a fit-out on the Gold Coast or in SEQ? Call us or request a free quote — fixed-price on site, full compliance stack included.