Most body corporate electrical jobs start the same way. A light is out in the car park, the intercom is playing up, or the emergency lights failed their test. Someone on the committee or the building manager rings an electrician. That’s fine for a small repair. It’s where problems start for anything bigger: one quote when two were required, a project split into pieces to fit under the limit, or a contractor whose insurance nobody checked.

This guide is for committee members, strata managers and building managers in Queensland. It covers the spending limits and quote rules, what to check about the contractor, when to ask for a SWMS, and how to brief an electrician so the quotes are comparable. It’s general information based on Queensland Government guidance for schemes under the Standard, Accommodation and Small Schemes modules. Commercial Module schemes work differently. Your body corporate manager can confirm what applies to your scheme.

Step 1: Know the two spending limits

Queensland body corporate rules use two different limits, and they’re often confused.

Limit What it controls Default if the body corporate hasn’t set one
Committee spending limit How much the committee can spend on one item or project without a general meeting resolution Number of lots × $200
Major spending limit When at least 2 quotes must be considered, whether the decision is made by the committee or at a general meeting The lesser of number of lots × $1,100, or $10,000

Both can be changed by ordinary resolution at a general meeting, so check your scheme’s minutes before relying on the defaults. The figures come from the Queensland Government’s pages on committee spending limits and major spending. The committee page also says the committee must allow for GST in its spending.

A worked example

Take a 25-lot building with default limits. The committee can spend up to $5,000 (25 × $200). The major spending limit is $10,000, because that’s less than 25 × $1,100. So:

Don’t split the job. The Queensland Government says the committee “cannot divide a single project into smaller parts in order to bring the project within its spending limit.” Replacing every car park light in three monthly invoices is still one project. A good contractor will quote the whole scope and let the committee decide how to stage it properly.

What about emergencies?

Under the government’s guidance, the committee can only spend over its limit if it’s authorised by an ordinary resolution, all owners consent in writing, an adjudicator has authorised it to meet an emergency, or it’s needed to comply with a statutory order or a court or adjudicator’s order. Making a dangerous situation safe on the night is usually a small cost. A larger repair that follows may need one of those approvals. Talk to your body corporate manager before you commit to a big emergency job.

Step 2: Get quotes that can be compared

Two quotes only help if they’re for the same thing. The most common problem we see is one electrician quoting “replace 20 fittings” and another quoting a full redesign. The committee then compares a cheap number against a complete one. Give every contractor the same brief:

  1. Describe the problem, not the solution. “Car park is too dark at night and fittings keep failing” gets better answers than “replace the lights”.
  2. Ask for an itemised scope. Fittings, quantities, labour, access equipment, disposal and testing listed separately.
  3. Ask what standard the work is designed to, where one applies, such as for car park or emergency lighting. Our strata car park lighting guide explains why this matters.
  4. Ask about exclusions and assumptions, such as switchboard capacity, after-hours access or making good.
  5. Ask for a fixed price, not an estimate, and how long it’s valid for.

The government’s major spending page says one quote may be enough in exceptional circumstances, where it isn’t possible to get two. For example, only one supplier can maintain a proprietary system. If that applies, record why in the minutes.

Step 3: Check the licence and insurance

Every contractor should give you an electrical contractor licence number that you can check on the Electrical Safety Office’s licence search. A worker licence isn’t enough on its own. We’ve set out how to check, and what the licence classes mean, in how to check an electrician’s licence in QLD.

On insurance, WorkSafe Queensland says an electrical contractor licence requires public and products liability insurance with a limit of indemnity of at least $5,000,000, and consumer protection insurance of at least $50,000. Ask for a certificate of currency before the first job and keep it on file. Diarise the expiry date, as well as the licence renewal, because contractor licences are issued for one year.

After the job, the contractor must give you a certificate of testing. WorkSafe says contractors must keep a copy for five years. The body corporate should keep its own copy too. Our compliance certificate guide explains what it shows.

Step 4: Safety on site and SWMS

Common property electrical work often involves ladders or elevated work platforms in car parks and stairwells, roof access, and live switchboards. That’s where a safe work method statement (SWMS) comes in.

WorkSafe Queensland says a business carrying out high risk construction work must make sure a SWMS is prepared before the work starts, that the work follows it, and that work stops if it doesn’t. A SWMS identifies the high-risk work, the hazards and risks, and the controls, and describes how those controls will be put in place and monitored. WorkSafe gives work where a person could fall more than 2 metres as one example. It also describes working on or near energised electrical equipment as high-risk work that SWMS help manage.

The contractor prepares the SWMS, not the committee. But it’s reasonable for the body corporate or building manager to ask for it before high-risk work starts, and a professional contractor will have one ready.

Is your body corporate a PCBU? Queensland Government guidance says a body corporate responsible only for residential common areas is generally not regarded as a PCBU (a person conducting a business or undertaking). It will be one if it employs any worker or is responsible for common areas used for commercial purposes, such as shops or restaurants. Then it has duties under the Work Health and Safety Act 2011. Mixed-use buildings should get advice on what that means for them.

Red flags when engaging an electrician

Step 5: Set it up once, not every time

For buildings with regular electrical work, it’s simpler to have the paperwork sorted in advance: an approved contractor with licence and insurance on file, a standing brief for common jobs, and a scheduled maintenance program. That way routine work happens within the committee’s limit, larger items come to the AGM with proper quotes, and testing such as emergency lighting checks isn’t left to chance. A fixed-price preventative maintenance plan helps with budgeting too.

If an owner wants work on common property for their own benefit, such as an EV charger, that’s a different approval path. See our EV charger body corporate approval guide. And if you’re unsure whether a fault is the body corporate’s or a lot owner’s to fix, start with body corporate vs unit owner electrical responsibilities.

Body corporate electrical work on the southern Gold Coast

We work with committees, strata managers and onsite managers in buildings from Broadbeach and Mermaid Beach down through Burleigh Heads, Palm Beach, Kirra and Coolangatta. Typical jobs include car park lighting, emergency and exit lighting, intercoms and access systems and switchboard work in multi-residential buildings.

As a strata and body corporate electrician, we quote in a format committees can vote on: fixed price, itemised scope, licence and insurance details attached, and a SWMS for high-risk work.

Frequently asked questions

How much can a body corporate committee spend without a vote in QLD?

It depends on the committee spending limit set by the body corporate by ordinary resolution. If no amount has been set, Queensland Government guidance says the default is the number of lots multiplied by $200. A 25-lot scheme would have a default limit of $5,000. The committee must allow for GST.

When does a body corporate need two quotes?

At least 2 quotes are needed for spending above the scheme's major spending limit. If the body corporate hasn't set one, the default is the lesser of $1,100 multiplied by the number of lots, or $10,000. For a general meeting decision, the 2 quotes must be included with the notice of meeting.

Can the committee split a job to stay under its spending limit?

No. Queensland Government guidance says the committee cannot divide a single project into smaller parts to bring it within its spending limit. If the whole project is above the limit, it needs a general meeting resolution or another approved authorisation, and two quotes if it is above the major spending limit.

Is one quote ever enough for major spending?

Queensland Government guidance says one quote may be enough in exceptional circumstances where it isn't possible to get two, such as when only one supplier can provide the item. Record the reason in the minutes so owners can see why only one quote was considered.

What insurance should an electrician have for strata work?

WorkSafe Queensland says an electrical contractor licence requires public and products liability insurance of at least $5,000,000 and consumer protection insurance of at least $50,000, in the business's legal name. Ask for a certificate of currency before work starts and note when it expires.

Do electricians need a SWMS for body corporate work?

A SWMS is required before high risk construction work, such as work where someone could fall more than 2 metres. WorkSafe Queensland also describes working on or near energised electrical equipment as high-risk work that SWMS help manage. The contractor prepares the SWMS, and it's reasonable for the building manager to ask to see it.

Is a residential body corporate a PCBU?

Queensland Government guidance says a body corporate responsible only for residential common areas is generally not regarded as a PCBU. It will be a PCBU if it employs any worker or is responsible for common areas used for commercial purposes, such as shops or restaurants, and then it has duties under the Work Health and Safety Act 2011.

Can the committee approve emergency electrical repairs over its limit?

Queensland Government guidance says the committee can spend over its limit if it's authorised by ordinary resolution, all owners consent in writing, an adjudicator authorises it to meet an emergency, or it's needed to comply with a statutory, court or adjudicator's order. Check with your body corporate manager before committing to a large emergency repair.

Need quotes for an upcoming committee meeting or AGM? Call us. Byron will inspect the job and send a fixed-price, itemised quote with licence and insurance details attached.